A 16 year-old NSW policy is constraining the local infrastructure funding available for new housing, even as the state asks councils to accommodate unprecedented growth

Spinifex is an opinion column. If you would like to contribute, contact us to ask for a detailed brief.

Under the National Housing Accord, NSW has committed to deliver 377,000 new homes between 1 July 2024 and 30 June 2029. It is rezoning land, accelerating assessments and asking councils to plan for substantial growth. Yet one part of the infrastructure funding system remains fixed in 2010.

The thresholds that generally trigger an independent review of a council’s section 7.11 contributions plan remain at $20,000 per dwelling or residential lot, or $30,000 on specified land. They have not been indexed since the two-tier framework commenced in September 2010.

Had those amounts merely kept pace with inflation, they would be about $30,900 and $46,300 by June 2026. The difference matters because land, roads, parks, community facilities and other infrastructure have become considerably more expensive to provide.

My preliminary analysis indicates that the policy may have suppressed between $360 million and $1.24 billion of potential local contribution capacity across NSW between 2010 and 2026. The central scenario is about $730 million in constant 2026 dollars.

That is a modelled estimate, not an audited measure of cash income foregone by councils. Actual collections depend on where development occurred, the contribution rates applying at the time, dwelling mix, credits, exemptions, planning agreements and when contributions were paid. The range is deliberately wide. Even with those qualifications, the scale warrants closer examination.

How the threshold creates a funding gap

A section 7.11 contributions plan is meant to identify the local infrastructure required because of development, establish the connection between development and that demand, estimate the reasonable cost, and apportion the cost fairly. The resulting rate is therefore based on an identified infrastructure program rather than an arbitrary charge.

Where the calculated contribution exceeds the applicable threshold, a council generally needs its plan reviewed by the IPART (Independent Pricing and Regulatory Tribunal) if it wants to levy the full amount. The review pathway provides scrutiny, which is appropriate. The problem is that it can be disproportionate for a moderate exceedance and does not readily accommodate every legitimate category of local infrastructure, particularly in established and infill areas.

The developer’s immediate contribution liability is lower than the amount calculated under the plan. Existing residents may subsidise the gap through rates and other general revenue. Future residents may wait longer for parks, roads and community facilities, or receive less infrastructure than the plan identified.

If a council does not use that pathway, the contribution imposed on development is constrained. The underlying infrastructure need does not fall by the same amount. The council must redesign or defer works, find money elsewhere, or accept a lower level of infrastructure provision.

This produces a win-lose-lose result. The developer’s immediate contribution liability is lower than the amount calculated under the plan. Existing residents may subsidise the gap through rates and other general revenue. Future residents may wait longer for parks, roads and community facilities, or receive less infrastructure than the plan identified.

The longer the thresholds remain fixed, the larger this mismatch becomes. Our indicative cost series suggests that between 2010 and 2026 infrastructure land costs increased by about 150 per cent, building costs by about 81 per cent and road costs by about 67 per cent. The thresholds increased by zero.

Infrastructure cost indices compared with the fixed contribution threshold, 2010 to 2026. The land-cost series is an indicative InfraGrowth estimate. Building and road series use published construction cost indices.

The City of Sydney shows the effect

The City of Sydney provides a useful case study because the same broad contributions plan framework has operated over a long period and the City publishes indexed contribution rates and annual financial information.

By June 2026, the uncapped contribution for a two-bedroom dwelling was approximately $23,900 to $30,500 across the City’s east, south and west precincts. The south precinct, which includes Green Square, carries most of the forecast growth used in the model.

Using published plan rates, residential activity indicators and recorded contribution income, I estimate an indicative cumulative effect approaching $90 million to 2026 for the local government area outside central Sydney. That represents about 20 per cent of recorded section 7.11 income over the modelled period.

Again, this is a counterfactual estimate rather than an audited City loss. It reconstructs what may have been collected if the threshold had moved with inflation and development activity had otherwise remained unchanged. It does not claim that every theoretical dollar would have been levied and paid.

The case study also exposes a weakness in the formal review route. My high-level diagnostic indicates that excluding works outside the essential works framework could leave the amount potentially recoverable below the projected income under the capped plan. In that circumstance, undertaking the review would not solve the funding gap.

City of Sydney cumulative recorded section 7.11 income and modelled income foregone. Indicative counterfactual for the local government area excluding Central Sydney. This is not an audited accounting loss

Around one quarter of forecast growth may be exposed

This funding pressure is no longer limited to greenfield development on Sydney’s fringe. As established suburbs accommodate more infill and higher-density housing, councils must expand and upgrade parks, community facilities, streets and other local infrastructure in locations where land and construction costs are often higher.

An initial screening exercise suggests that about 15 per cent of the state’s 2024–29 housing target may be in areas covered by an IPART-reviewed plan. A further 26 per cent, or about 96,500 dwellings in the central case, may be in areas where a section 7.11 plan exceeds the threshold but has not been reviewed and may therefore be constrained. The remaining 59 per cent includes section 7.12 areas, sub-threshold plans and other locations.

This allocation is a point-in-time screening estimate. Some section 7.11 plans currently below the threshold may reach it during the five-year housing-target period as contribution rates and infrastructure costs continue to rise. The share of forecast housing exposed to the threshold could therefore increase over time.

These are modelled allocations pending detailed plan-area mapping. The central result nevertheless indicates that the threshold is relevant to a material share of the state’s housing program, not a small collection of legacy growth areas.

Indicative allocation of the NSW 2024–29 housing target. The shares are based on an InfraGrowth screening model and remain subject to detailed plan-area mapping

Alternative levies, rates and grants do not repair the policy

Councils may instead use a section 7.12 levy, which is generally capped at 1 per cent of development cost. Under the department’s section 7.12 practice note, a council may seek the minister’s approval for a higher-rate levy of up to 3 per cent, supported by a costed infrastructure program and reasonable apportionment of costs to development.

However, this pathway does not resolve the section 7.11 threshold problem. The criteria generally limit higher-rate levies to identified growth areas or precincts, while the effect of the unindexed thresholds may extend across an entire local government area, including established areas outside designated growth precincts.

The City of Sydney is a clear example. Even at 3 per cent, the levy would typically raise only about $18,000 to $22,000 per apartment—barely above the $20,000 section 7.11 threshold, if at all, and well below many uncapped contribution rates. A higher-rate section 7.12 levy may be useful in suitable precincts, but it is neither geographically broad enough nor financially sufficient to repair the loss of section 7.11 funding capacity since 2010.

Councils can seek a special rate variation, and government grants can help fund particular projects. Neither provides a sound structural substitute for predictable contributions linked to development demand.

A special rate variation requires a council decision, community engagement and IPART approval. Rate revenue also accumulates over time and may not match the location or timing of infrastructure needed for growth. Most importantly, it transfers development-attributable costs to existing residents and businesses.

Grants play a valuable role, particularly where a project has broader regional or state benefits. But programs are commonly competitive, discretionary and subject to changing priorities. Eligibility requirements, co-funding and program timing may not align with the council’s works program. A grant can deliver a project while leaving the policy setting that created the funding gap untouched.

This may also help explain part of the large balance of unspent local contributions held by NSW councils. Unspent balances are often presented simply as evidence that councils are failing to deliver.

In some cases, however, a council may have collected the development share of a project but still be unable to proceed because it cannot fund the threshold-related gap, other unapportioned costs or escalating delivery costs.

Removing the cap gap would not resolve every cause of delayed expenditure, but it would put councils in a stronger position to convert collected contributions into infrastructure that supports housing growth.

The state already indexes its own contribution

The inconsistency is difficult to ignore. NSW indexes its housing and productivity contribution every quarter using a construction cost index. This protects the purchasing power of the state contribution. Local section 7.11 thresholds, which matter greatly to councils’ capacity to fund local infrastructure, remain frozen.

The housing and productivity contribution has also absorbed part of the development industry’s capacity to pay during a period of weak feasibility. That has made an increase in local thresholds politically harder, even though the state contribution funds only a modest share of the State infrastructure program and local contributions carry much greater relative weight in council capital programs.

Housing feasibility is a real concern. Simply adding a CPI adjustment to the local threshold without considering the combined contribution burden may meet resistance and affect marginal projects. One option worth testing is a rebalancing between state and local charges.

For a greater Sydney apartment at July 2026 rates, replacing the base apartment component of the Housing and productivity contribution with a CPI reset of the $20,000 local threshold would leave the combined amount almost unchanged.

That example is illustrative and would require detailed policy and feasibility testing. It shows, however, that restoring local infrastructure funding need not mean an equivalent increase in the total contribution burden.

A practical reform agenda

The immediate reform is straightforward. NSW should reset the $20,000 and $30,000 thresholds to reflect at least part of the real value lost since 2010, then index them automatically using a transparent published measure.

The government should also review the IPART pathway. A proportionate process could preserve independent scrutiny while allowing moderate threshold exceedances to be assessed more efficiently. The essential works framework should be reconsidered for established and infill settings where legitimate development-generated needs extend beyond a narrow infrastructure list.

The government should also review the criteria for approving higher-rate section 7.12 levies. The current practice note focuses largely on defined growth areas and precincts, limiting its usefulness for councils experiencing dispersed infill growth across an established local government area.

Allowing higher-rate levies for appropriately justified LGAs (local government areas) could provide a workable alternative for some councils whose section 7.11 rates have already reached the $20,000 threshold, as well as councils with currently sub-threshold rates that are likely to reach it in the coming years.

This would not replace section 7.11, where a higher contribution can be supported by clear nexus, reasonable costs and apportionment, nor would a levy of up to 3 per cent recover the funding capacity lost through 16 years of non-indexation. But it would give councils a more flexible option where an LGA-wide percentage levy is better suited to the pattern of development and infrastructure demand.

This is an uncomfortable issue to raise during a housing affordability and development feasibility crunch. Councils have little incentive to draw attention to their inability to fund infrastructure. Developers understandably prefer the lower liability. The state has little appetite for a change that may attract claims of higher housing costs.

But delaying reform does not remove the cost. It determines who pays it and whether the infrastructure is delivered. If NSW wants councils and communities to accommodate more housing, it must give them a funding framework that keeps pace with the cost of doing so.

A policy designed around 2010 prices should not continue to determine infrastructure outcomes in 2026.

See the full briefing, including the methods and qualifications.


Jonathon Carle, InfraGrowth Planning

Jonathon Carle is the founder and director of InfraGrowth Planning. He has more than 25 years’ experience in infrastructure planning and funding across local government, state government and consulting, with a particular focus on local infrastructure contributions, planning agreements and infrastructure funding strategies. More by Jonathon Carle, InfraGrowth Planning